By GloryOptics Technical Content Team · Published Nov 25, 2026 · Last updated Nov 25, 2026
On the afternoon of Friday, November 13, 2026, the U.S. Federal Aviation Administration (FAA) halted departures nationwide after air traffic control communications and radar data began dropping in and out. In its public Q&A and a Department of Transportation briefing, the FAA and DOT said the disruption coincided with routine line work: contractor L3Harris was moving a remote site in El Dorado, Arkansas, from legacy copper lines to fiber and installing new equipment there. The FAA also attributed the instability to legacy time-division multiplexing (TDM) equipment while noting that the root cause remained under investigation - a preliminary account, not a final finding.
No final root cause report has been published yet. The public record still shows where brownfield migrations carry risk. A new fiber route can pass every optical test while the service on it fails, because the new and legacy equipment interact badly or because nobody can isolate the change and fall back quickly enough.
This article sets out what is known about the outage and then gives a pre-cutover checklist with three separate sign-offs: the new fiber link meets spec, new and old equipment work together, and the service can be switched over or rolled back if something goes wrong. The checklist is general practice for migration projects and is not derived from the cause of this incident.
Scope note: GloryOptics has no role in the FAA network or the investigation. Everything below about the incident comes from public statements, FAA notices and press reports, each linked at the point of use. Causes that have not been officially confirmed are marked as open. This is editorial analysis of public statements, not an official finding; no final root cause report has been published as of the date above. We cover this incident because copper-to-fiber cutovers are routine work for the operators, installation contractors and passive-component buyers we supply; no product recommendation in this article depends on the outcome of the investigation.
What happened on November 13
The FAA Telecommunications Infrastructure (FTI) network carries voice and data circuits for U.S. air traffic control. L3Harris has operated it for many years; its predecessor, Harris Corporation, first won the FTI contract in 2002 (DOT Office of Inspector General audit). According to Duffy, the disruption occurred while L3Harris was migrating the El Dorado site from copper to fiber and deploying new equipment (DOT briefing, Nov 14).
| Time (U.S. Eastern) | What happened | Sources |
|---|---|---|
| Nov 13, about 3:30 pm | The FAA recorded disruptions to air traffic control communications and radar data. 17 of the 22 Air Route Traffic Control Centers were affected; some radio frequencies and radar feeds stayed available throughout. | FAA Q&A |
| Nov 13, 3:54–8:19 pm | The FAA Command Center issued a nationwide ground stop at 3:54 pm. The FAA says traffic resumed at 8:15 pm, and the advisory formally cancelling the ground stop went out at 8:19 pm. Roughly 12,462 flights were cancelled that day; the FAA notes that some of those cancellations had other causes. | Ground stop advisory · Cancellation advisory · FAA Q&A |
| Nov 14–15 | Duffy linked the disruption to new equipment deployed during the copper-to-fiber work. The FAA named El Dorado and Amarillo, Texas, as two possibly related sites and said the network stabilized after both were isolated. L3Harris said it would support the investigation. | DOT briefing · FAA Q&A · L3Harris statement |
| Nov 16–19 | Senators wrote to the FAA and DOT asking about primary and backup paths, common points of failure and fallback capability. On Nov 17, Duffy said the El Dorado anomaly had been reproduced in testing and the root cause was still being determined. On Nov 19, Reuters reported that FAA Administrator Bryan Bedford expected the findings to be made public. | Senators' letter · DOT investigation update · Reuters (syndicated copy) |
| Nov 23 | In an interview with CRN, HPE CEO Antonio Neri identified the "router" mentioned in FAA briefings as a Juniper circuit-to-packet (CTP) platform. HPE's position is that the device worked as configured, with a multicast feature enabled that this application did not need. | CRN interview |
What Duffy, L3Harris and HPE have said
The Transportation Secretary: equipment, installation and response time
Duffy has named both the equipment and the way it was installed as lines of investigation. The Associated Press reported that he also believes the ground stop could have been shorter if L3Harris had detected and isolated the anomaly sooner. That view will need alarm logs and response records to back it up. His comments came alongside a request, made with Bedford, for an additional $50 billion for air traffic control modernization. (DOT update and budget briefing · AP report)
The contractor: migration progress and funding
In its public statement, L3Harris said that it, its telecom partners and the FAA had completed more than 70% of the planned copper-to-fiber work (L3Harris statement). According to press accounts, the company also said it and the carriers had warned the FAA for years that aging lines needed replacing, but no dedicated funding had been provided to speed that work up (Fast Company). These are L3Harris's own claims and are attributed as such.
The equipment vendor: configuration and multicast
HPE, which now owns Juniper, says the CTP device behaved as configured and that multicast was enabled at the time (CRN interview). This is HPE's account. The investigation still has to establish what role multicast played in the failure, who approved the configuration, and how the device interacted with the legacy systems around it.
What the record supports about the cause
| Layer | What has been reported | What is still open |
|---|---|---|
| Direct failure mechanism | The FAA reports abnormal traffic on the FTI network, about 1,000 connection attempts every 4 to 5 seconds, followed by instability in legacy equipment that disrupted air traffic control (ATC) communications and radar data. Isolating the related sites stabilized the network. (FAA Q&A) | The original trigger, and what each of the two sites contributed. |
| System factors that may have widened the impact | In our reading, a circuit-to-packet device sits between new packet transport and existing time-division multiplexing (TDM) circuits, so compatibility with legacy equipment is a natural focus. The Government Accountability Office has already flagged aging ATC systems and weak modernization program management as risks. (GAO audit) | Whether the anomaly could have been contained at one site, and whether primary and backup paths shared critical equipment, links or other dependencies. The senators' letter asks exactly this. (Senators' letter) |
| Oversight and change process | The FAA says work at remote sites has often been done during daytime hours and that it will reassess maintenance windows. (FAA Q&A) Citing anonymous people close to the investigation, The Washington Post reported that FAA personnel were on site to oversee, test and sign off on the work - this has not been officially confirmed. (Washington Post) | Whether a sign-off took place and, if so, which tests it covered; whether live service and failover were part of acceptance; when alarms reached the right people; and who had authority to halt the change or roll it back. |
The defensible summary today: the communications disruption happened during copper-to-fiber maintenance, abnormal traffic was linked to instability in legacy systems, and the specific root cause is still awaiting official confirmation.
A pre-cutover checklist for copper-to-fiber migrations
Most copper-to-fiber projects are far smaller than a national carrier backbone, but they share the same structure: a new passive route, new active equipment at each end, and legacy systems that must keep running until the last circuit moves. A clean optical test is not the same as a working service, so the checks below separate physical-link acceptance from service operation and rollback capability. Each item names an owner and the evidence that should exist before the change is released.
Figure 1. Three gates before a cutover is released. Physical-link acceptance includes end-to-end loss testing and any OTDR checks required by the test plan. Service operation (new/legacy compatibility and primary/backup path independence) and rollback capability each need a named owner and their own evidence. The four checks in the table below map onto these three gates.
| Check | Owner | Evidence required before release |
|---|---|---|
| Fiber link acceptance | Installation and acceptance team | Route map, fiber-to-port mapping table and end-face inspection records (IEC 61300-3-35). End-to-end insertion loss measured with an optical loss test set (OLTS) at 1310 and 1550 nm against a documented link loss budget; pass = measured loss ≤ budget. Reflectance/ORL within the project spec. For long outside-plant links with splice points, optical time-domain reflectometer (OTDR) traces taken bidirectionally and averaged at splice points, as defined in the project acceptance test plan. Fiber type (OS2 / G.652) and polarity confirmed against the fiber-to-port mapping table. |
| New/legacy equipment compatibility | Network engineering team | Approved configuration baseline, a second-person review record, and service and failover tests run in an isolated environment with representative new and legacy equipment, including TDM-to-packet interworking and a review of features enabled but not required by the service. |
| Primary/backup path independence | Network architecture and operations team | A dependency map that marks shared equipment, power, ducts and splice closures, plus results showing service actually transfers when the primary path fails. |
| Cutover window and rollback | Operator's change owner | Single-site pilot plan, low-traffic window, metrics to watch, stop and rollback criteria, the named person who can authorize rollback, and drill records. Wider rollout is approved only after the pilot passes acceptance. |
The first row covers the physical link sign-off; rows 2 and 3 together cover service operation; row 4 covers rollback capability. An OTDR trace is one part of physical-link acceptance.
For the fiber acceptance row, general test methods for outside-plant work are covered in the FOA outside plant testing guide; the pass criteria above come from the project's own loss budget and acceptance test plan, not from a general reference. Splice-point and closure checks are covered in our OSP cable splicing checklist. Where the migration reaches the customer-side handoff, it is worth reviewing the fiber network interface device (NID) and the copper demarcation point, since that is where the new link meets equipment the operator may not control.
The project lead should write the acceptable service thresholds and the observation period into the change ticket, then collect three separate sign-offs: physical link, service operation and rollback capability. This mirrors standard change-management practice: documented hazards, named responsibilities and rehearsed contingency procedures. The FAA's own Safety Management System and emergency operations order JO 1900.47G are one example of that approach, not a requirement that applies to private networks.
The acceptance evidence above depends on the passive components selected for the same route - see Passive components for a copper-to-fiber route for the GYTA53 cable, splice closures, ODF and LC/UPC OS2 patch cords, each with what to confirm before quoting.
If a cutover goes wrong: restore, verify, then redeploy
Figure 2. The decision path for a controlled cutover. A single-site pilot runs in a low-traffic window while the team watches agreed metrics; any stop criterion hands authority to the named rollback owner. Wider rollout is approved only after the pilot passes acceptance and service stays stable through the observation period.
- Restore service and preserve evidence. Freeze similar changes. Have the authorized team isolate the faulty segment and switch back to the verified service path, following the contingency plan. At the same time, secure the before-and-after configurations, alarms, operator logs and timestamps. In this incident, the FAA has publicly confirmed it isolated the related sites, disabled the relevant function and paused installation of the same type of equipment. (FAA Q&A)
- Verify the fix before redeploying. The operator, contractor and equipment vendor should review the configuration and device interaction together and prove the correction in an isolated environment. Before the pilot resumes, re-run acceptance on live service, failover and rollback - a practice consistent with the FAA's contingency-planning approach (FAA JO 1900.47G).
- Turn long-term fixes into results that can be re-tested. Assign an owner, a deadline and a re-test condition to each corrective item: legacy equipment retirement, removal of shared dependencies, and the contractor's alarm escalation process. Use drills to measure how long detection, isolation, switchover and recovery actually take.
What is still unknown (as of November 25, 2026)
As of this writing, we found no published final root cause report and no public technical response to the senators' November 16 letter (FAA Q&A · Senators' letter). Three questions remain open:
- Root cause: what triggered the anomaly, what each of the two sites contributed, and how multicast relates to the failure.
- Change and acceptance records: who reviewed the equipment configuration, which tests the on-site sign-off covered, and when alarms appeared and were escalated.
- Path diversity and fallback: whether primary and backup paths shared a common point of failure, and how far the failover and rollback procedures were actually carried out.
We will update this article when the FAA publishes its findings.
Passive components for a copper-to-fiber route
The list below follows a typical cabling path from the outside plant to the equipment rack. It covers passive fiber components only. Active equipment such as circuit-to-packet platforms is outside GloryOptics' scope.
Figure 3. Four passive positions along the cabling path, from outside plant to equipment rack: outdoor backbone cable, outdoor splice closure, rack-mount optical distribution frame and the patch cord into active equipment. Each passive position corresponds to a product below; the active equipment at the right-hand edge is outside the scope of this list.
A candidate when the project calls for a double-sheath armored design. Confirm installation method (duct or direct burial), fiber count, cable diameter and bend radius.
Use where heat-shrink sealing is specified. Confirm cable entry diameters, splice tray capacity, spare fibers and how the closure will be re-entered for maintenance.
Size by rack dimensions, port count, adapter type and planned expansion.
For duplex single-mode links with LC/UPC on both ends. Confirm length and polarity.
Get a passive bill of materials checked before cutover
Send us your route map, cable diameter and fiber count, port table, bill of materials and required test report format. GloryOptics' team will check your passive fiber component configuration against the route and flag gaps before you place the order.
Request a fiber cabling quote →
Sources
- FAA, Nationwide ground stop: questions and answers
- FAA ATCSCC, Ground stop advisory, Nov 13, 2026 and cancellation advisory
- U.S. DOT, Secretary Duffy update on airspace restoration (Nov 14) and investigation update (Nov 17)
- DOT Office of Inspector General, FTI audit report
- U.S. Senate Commerce Committee, Letter to DOT and FAA, Nov 16, 2026
- GAO, Air traffic control modernization audit
- L3Harris, Statement on the Nov 13 ground stop
- CRN, Interview with HPE CEO Antonio Neri
- Associated Press, report on Duffy's comments
- Reuters (syndicated copy via Investing.com), U.S. plans to announce cause of outage
- The Washington Post, FAA oversaw, signed off on repair work
- Fast Company, The FAA was warned about its telecom upgrade
- C-Fiber (iccsz.com), Chinese-language report - background reading only, not used as a primary source
- Fiber Optic Association, Testing outside plant fiber
- FAA, Safety Management System for air traffic and Order JO 1900.47G
- GloryOptics, OSP cable splicing checklist and the fiber NID and the copper demarcation point